The 63 kV Eyvanekey substation optimization project was carried out in Semnan Regional Electricity Company with a credit of 3.9 billion Rials.

According to the information base of the Ministry of Energy (Pawn), “Mehdi Moeini”, Director of Center and West Transmission Affairs of Semnan Regional Electricity Company, added: “In this project, the operation of changing tables and repairing post access roads according to the old The substation was done and the final asphalt was done to improve the traffic of the operation crews and repair groups.